A product whose work content time = 50 min is to be assembled on a manual production line. The… 1 answer below »

A product whose work content time = 50 min is to be assembled on a manual production line. The required production rate is 30 units/hr. From previous experience with similar products, it is estimated that the manning level will be 1.25. Assume that the proportion up-time E = 1.0 and that the repositioning time Tr = 0. Determine: (a) cycle time and (b) ideal minimum number of workers required on the line. (c) If the ideal number in part (b) could be achieved. how many workstations would be needed?