Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide…

Your project sponsor has requested a cost estimate for the project on which you’re working. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide to use ___________________.

A. Analogous estimating techniques

B. Bottom-up estimating techniques

C. Parametric estimating techniques

D. Three-point estimating techniques