If a worker earns $30 per hour in salary but the project is charged $75 per hour for each hour… 1 answer below »
If a worker earns $30 per hour in salary but the project is charged $75 per hour for each hour the individual works, then the overhead rate is:
A. 100%
B. 150%
C. 250%
D. None of the above