Please fill in the box the answers.. Question4 Given the following information, the project network. Compute ES, EF, LS, LF and slack times for the project network. Lag 5 Lag 10 Lag 8 Lag 7 4 Lag 4 ES ID EF SL LS Dur LF Lag 10 Lag 8 SL 4