Senior management asks Kate to take over a project already in the planning phase. She realizes that.

Senior management asks Kate to take over a project already in the planning phase. She realizes that the estimates created are not sufficient. What would you advise she do?

a) Kate needs to use the estimates that she was given, otherwise the project has to start over again

b) Kate needs to confirm the top-down estimate with management and then engage the project team to execute a correct bottom up estimate

c) Kate needs to get the top-down estimate from senior management and use that as the correct estimate for completing the project

d) Kate should let senior management know that she doesn’t want the manage the project because the estimates are insufficient