The cost or financial baseline of a project is composed of: A. Distributed budget only B…. 1 answer below »
The cost or financial baseline of a project is composed of:
A. Distributed budget only
B. Distributed and undistributed budgets only
C. Distributed budget, undistributed budget, and the management reserve only
D. Distributed budget, undistributed budget, management reserve, and profit only