Using Table 12–4, draw the CPM chart for the project. In this case, make all identifications on… 1 answer below »

Using Table 12–4, draw the CPM chart for the project. In this case, make all identifications on the arrows (activities) rather than the events. Show that the critical path is twentyone weeks.

Using Table 12–5, draw the precedence chart for the project, showing interrelationships. Try to use a different color or shade for the critical path.

Calculate the minimum cash flow needed for the first four weeks of the project, assuming the following distribution

Furthermore, assume that all costs are linear with time, and that the activity X cost must be spent in the first two weeks. Prove that the minimum cash flow is $92,000.

 

 

"Get 15% discount on your first 3 orders with us"
Use the following coupon
FIRST15

Order Now