A project related information is provided in the table. Select only correct answers. Activity Predec

A project related information is provided in the table. Select only correct answers.

Activity

Predecessor

Normal Time/week

Min Time/week

Normal Cost

Crash Cost

A

0

14

11

$1,500

$2,830

B

A

5

3

$1,200

$2,160

C

A

10

7

$2,000

$3,590

D

B, C

8

5

$900

$2,500

E

D

6

4

$1,400

$2,150

F

D

9

6

$1,500

$3,100

G

E, F

7

5

$960

$1,900

H

G

15

14

$1,900

$2,340

Activity

ES

EF

LS

LF

Slack, LS-ES

A

0

14

0

14

0

B

14

19

19

24

5

C

14

24

14

24

0

D

24

32

24

32

0

E

32

38

35

41

3

F

32

41

32

41

0

G

41

48

41

48

0

H

48

63

48

63

0 a.

When G crashed maximally, the incremental cost is $440 b.

The activity to be considered first for crashing is H c.

the total cost under normal condition is not $11,360 d.

if manager intends to reduce completion by 6 weeks, the incremental cost is $2,710 e.

The total weeks can be crashed is 14 f.

if manager intends to reduce completion by 6 weeks, the total cost is $14,070 g.

maximally, A’s duration can be crashed (weeks) by 3 h.

the total cost with crash is $20,670