As the project manager, you decided to arrange a team meeting to identify and analyze lessons learne

As the project manager, you decided to arrange a team meeting to identify and analyze lessons learned from quality control with stakeholders. What should you do with them?10o Document them and make them part of the historical database for the project and the performing organization.o Discuss them with management and make sure that they remain otherwise confidentialo Publish them in the corporate newsletter.o Follow your strategic decisions, independent from lessons learned. These decisions have been made and should be implemented whatever the outcomes are.