If BCWS 1000, BCWP 1200, and ACWP 1300, the project is: A. Ahead of schedule and under budget …. 1 answer below »

If BCWS  1000, BCWP  1200, and ACWP  1300, the project is:

A. Ahead of schedule and under budget .

B. Ahead of schedule and over budget

C. Behind schedule and over budget

D. Behind schedule and under budget

 