If BCWS 1000, BCWP 1200, and ACWP 1300, the project is: A. Ahead of schedule and under budget …. 1 answer below »
If BCWS 1000, BCWP 1200, and ACWP 1300, the project is:
A. Ahead of schedule and under budget .
B. Ahead of schedule and over budget
C. Behind schedule and over budget
D. Behind schedule and under budget