Refer to the information below:DependsOnOptimistic Duration(days)Most Likely Duration(days)Pessimist

Refer to the information below:DependsOnOptimistic Duration(days)Most Likely Duration(days)Pessimistic Duration(days)A-71018BA3814CB101422DA259EB,D7915FC,D4919GB101529HC,E,F2819IG,H127JI3918Determine the following for each activity:Expected Duration (round to the nearest whole number)Early Start (ES)Early Finish (EF)Late Start (LS)Late Finish (LF)Total Float (TF)VarianceDetermine the following for the project:Critical Path (CP)Number of Days required to complete the project (i.e., Expected Project Duration)Determine the probability that the project will complete in 76 days or less.Determine the probability that the project will complete in 58 days or less.

"Get 15% discount on your first 3 orders with us"
Use the following coupon
FIRST15

Order Now